Practice SetConstruction Management

Construction Management MCQ Practice Set — 35 Questions with Answers

35 exam-oriented Construction Management multiple-choice questions with the correct answer and a clear explanation for each. Frequently asked in AE Level Civil Engineering, JE Level Civil Engineering. Solve the full set below for free — no login required.

  1. 1
    Construction EquipmentMEDIUM

    A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes. Working at 50 productive minutes per hour, the output per hour is:

    A5.0 m³/hr
    B6.25 m³/hr
    C8.33 m³/hr
    D10.0 m³/hr

    Answer: C. 8.33 m³/hr

    Explanation: Productive cycles/hr = 50 min ÷ 3 min = 16.67 cycles. Output = 16.67 × 0.5 m³ = 8.33 m³/hr. Efficiency factor accounts for changeover, setup and minor delays; a 50/60 ratio (83%) is standard for batching plants.

  2. 2
    Contract ManagementMEDIUM

    In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:

    AThe client — all risks lie with the owner
    BThe contractor — who quoted a fixed price for the entire scope
    CShared equally between client and contractor
    DCovered by the contingency fund maintained by the government

    Answer: B. The contractor — who quoted a fixed price for the entire scope

    Explanation: In a lump sum/fixed-price contract, the contractor bears cost overrun risk as they have quoted one total price. This contrasts with item-rate contracts where payment adjusts to actual quantities. Contractors factor site risks into their lump sum quote.

  3. 3
    Original practiceMEDIUM

    A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is

    A20 m³
    B3.5 m³
    C7 m³
    D14 m³

    Answer: C. 7 m³

    Explanation: Volume of brick masonry = Length × Height × Thickness = 5 × 4 × 0.35 = 7 m³ m³. In building estimation, brick wall quantities are computed as the gross volume (deductions for openings done separately). Standard brick sizes in India: 190×90×90 mm with mortar joints of 10 mm.

  4. 4
    Project CrashingMEDIUM

    An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days and crash cost Rs.14,000. The cost slope is:

    ARs. 1,000/day
    BRs. 2,000/day
    CRs. 4,000/day
    DRs. 6,000/day

    Answer: B. Rs. 2,000/day

    Explanation: Cost slope = (Crash cost − Normal cost)/(Normal duration − Crash duration) = (14,000 − 8,000)/(10 − 7) = 6,000/3 = Rs. 2,000/day. Lower cost slope = cheaper to crash; crash this activity first in network crashing.

  5. 5
    Tender DocumentsMEDIUM

    Which of the following is issued AFTER a contract is awarded and is NOT a tender document?

    ANotice Inviting Tender (NIT)
    BBill of Quantities (BOQ)
    CLetter of Acceptance (LOA)
    DGeneral Conditions of Contract (GCC)

    Answer: C. Letter of Acceptance (LOA)

    Explanation: NIT, BOQ, GCC, drawings and technical specifications are all tender documents issued to bidders before bid submission. LOA is sent to the successful bidder after evaluation to formally accept their offer — it is a post-tender document that converts the accepted bid into a contract.

  6. 6
    Original practiceMEDIUM

    One face of a wall 5 m by 3 m is to be plastered. Plastering area is

    A15 m²
    B30 m²
    C8 m²
    D7.5 m²

    Answer: A. 15 m²

    Explanation: Plastering area (surface area) = length x height (m^2) for one face of a wall. Per IS 1200 Part 14, plastering is measured as the actual plastered area in m^2. Deductions are made for openings (doors, windows) above 0.5 m^2; additions for reveals, jambs, and soffits if not measured separately. Area = length × height = 15 m².

  7. 7
    PYQ/PYQ-PatternMEDIUM

    If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is

    ARs. 12500
    BRs. 25000
    CRs. 50000
    DRs. 5005

    Answer: B. Rs. 25000

    Explanation: Bill of quantities amount = measured quantity x unit rate (Rs.). In building estimation, cost = measured volume/area x analysis-of-rates unit cost. The abstract of cost aggregates all item amounts to give project total cost. Add GST and contractor overhead/profit to arrive at the contract (tender) value. Amount=quantity×rate=5×5000=Rs. 25000.

  8. 8
    Network AnalysisMEDIUM

    Independent float of an activity is the maximum delay that can be used without affecting:

    AThe early start of successor activities
    BThe early start of successor activities and the late finish of predecessor activities
    CThe total float of preceding activities
    DThe critical path length of the project

    Answer: B. The early start of successor activities and the late finish of predecessor activities

    Explanation: Independent float is the amount of time an activity can be delayed without affecting the early start of any successor activity or the late finish of any predecessor activity. It is calculated as: IF = ES_successor - LF_predecessor - Duration_activity (if negative, IF = 0).

  9. 9
    Construction ManagementMEDIUM

    In the PERT technique, the critical path has slack equal to

    Aalways zero
    Bpositive value
    Cnegative value
    Dzero

    Answer: D. zero

    Explanation: In PERT/CPM, the critical path is defined as the path with zero slack (or minimum slack in a network). While negative slack can exist in constrained projects, the standard definition of the critical path is zero slack.

  10. 10
    Contract Types ClassificationMEDIUM

    A lump-sum (fixed-price) contract is most appropriate when:

    AThe scope of work is uncertain and likely to change frequently
    BThe scope, drawings, and specifications are well-defined at the time of tendering, and the contractor takes the risk of cost overrun
    CThe project involves complex unknowns best managed on cost-plus basis
    DSpeed of construction is the only priority

    Answer: B. The scope, drawings, and specifications are well-defined at the time of tendering, and the contractor takes the risk of cost overrun

    Explanation: Lump-sum contract: total price fixed at award; scope fully defined in tender documents. Contractor bears cost-overrun risk; employer bears scope-change risk (variations). Suitable for building construction with complete designs. Cost-plus (reimbursable) is used for uncertain scope (emergency, refurbishment). Unit-rate contract is used for earthwork, road work where quantities vary.

  11. 11
    Estimating, Costing and Construction ManagementEASY

    The process of determining present worth of a property is called:

    ATendering
    BValuation
    CIndenting
    DGauging

    Answer: B. Valuation

    Explanation: Valuation estimates the current monetary worth of a property or asset.

  12. 12
    GeneralMEDIUM

    A revised estimate is prepared when

    Aonly measurement book is lost
    Bsanctioned estimate is likely to be exceeded beyond permissible limit
    Cno design change occurs
    Dwork is completed exactly at original amount

    Answer: B. sanctioned estimate is likely to be exceeded beyond permissible limit

    Explanation: Revised estimate is needed for material changes or cost escalation beyond allowed limits.

  13. 13
    Quality ControlMEDIUM

    As per IS 456:2000, the minimum number of samples of concrete to be taken per day's pour for a structure is:

    A1 sample per 5 m³ — no minimum frequency
    B1 sample per 50 m³ but not less than 4 samples per day of pour
    C2 samples per day regardless of volume
    D1 sample per batch regardless of volume

    Answer: B. 1 sample per 50 m³ but not less than 4 samples per day of pour

    Explanation: IS 456:2000 Cl. 15.2.2: Minimum frequency of sampling = 1 sample per 50 m³ or per day of pour, whichever requires more samples, but not less than 4 samples for a day's pour when volume > 30 m³. Each sample = 3 cubes (tested at 7 days, 28 days). This ensures statistical validity.

  14. 14
    Construction SequenceMEDIUM

    The correct sequence for brick masonry construction of a load-bearing wall is:

    AFoundation → scaffolding → brick laying → curing → plastering
    BFoundation → brick laying → scaffolding → plastering → curing
    CScaffolding → foundation → brick laying → curing → plastering
    DFoundation → brick laying → curing → scaffolding → plastering

    Answer: A. Foundation → scaffolding → brick laying → curing → plastering

    Explanation: Foundation is excavated and laid first. Scaffolding is erected at ground level before masonry begins and raised as height increases. Brick laying proceeds course by course. Curing of mortar joints must begin soon after laying and continue for 7 days. Plastering after masonry has set sufficiently (7–14 days minimum).

  15. 15
    GeneralMEDIUM

    The plinth area of a building is measured at

    Afloor level including wall thickness
    Bfoundation bottom only
    Ccentre line of road
    Droof top only excluding walls

    Answer: A. floor level including wall thickness

    Explanation: Plinth area is covered built-up area measured at floor/plinth level.

  16. 16
    GeneralMEDIUM

    In rate analysis, contractor’s profit is commonly added as a percentage of

    Aonly cement weight
    Bonly water charges
    Ccost of materials, labour, equipment and overheads
    Donly salvage value

    Answer: C. cost of materials, labour, equipment and overheads

    Explanation: Contractor’s profit is added over the estimated cost components.

  17. 17
    Estimate TypesMEDIUM

    A 'revised estimate' in public works is prepared when the sanctioned amount is likely to be exceeded by more than:

    A2.5%
    B5%
    C10%
    D15%

    Answer: B. 5%

    Explanation: As per general financial rules, a revised estimate must be prepared when the probable cost of the work exceeds the sanctioned amount by more than 5%. It must be submitted for fresh approval before expenditure exceeds sanction. A supplementary estimate is prepared for additional work not included in original scope.

  18. 18
    Formwork StrikingMEDIUM

    As per IS 456:2000, the minimum period after casting before formwork (shuttering) of vertical faces of columns and walls may be removed is:

    A6 hours
    B16–24 hours
    C3 days
    D7 days

    Answer: B. 16–24 hours

    Explanation: IS 456:2000 Table 5 (Stripping times): Vertical faces of beams and columns = 16–24 hrs. Soffit of slabs (with props) = 3 days. Soffit of beams (props remaining) = 7 days. Removal of props for beams spanning ≤6 m = 14 days. Earlier stripping risks cold joint and surface damage.

  19. 19
    Earned ValueMEDIUM

    A project has SPI (Schedule Performance Index) = 0.85. This indicates that the project is:

    A15% ahead of schedule
    BBehind schedule — earning only 85 paise of work for every rupee of planned work
    C15% over budget
    D85% physically complete

    Answer: B. Behind schedule — earning only 85 paise of work for every rupee of planned work

    Explanation: SPI = EV/PV. SPI < 1 means project is behind schedule (earning less value than planned). SPI = 0.85 means for every Rs.100 of work planned, only Rs.85 worth is actually accomplished. CPI = EV/AC measures cost performance. SPI > 1 = ahead of schedule; SPI < 1 = behind.

  20. 20
    TenderMEDIUM

    The earnest money deposit (EMD) in a public tender serves to:

    ACover the contractor's material procurement costs
    BEnsure the successful bidder does not withdraw before executing the contract agreement
    CProvide a fund for defect rectification after project completion
    DAct as an advance payment for mobilisation

    Answer: B. Ensure the successful bidder does not withdraw before executing the contract agreement

    Explanation: EMD (bid security) protects the tender authority: if the L1 bidder withdraws after acceptance or refuses to sign, EMD is forfeited. Typically 2–5% of estimated project cost. EMD of unsuccessful bidders is refunded promptly; successful bidder's EMD is adjusted against security deposit after signing.

  21. 21
    Contract ManagementMEDIUM

    The defects liability period (DLP) in most standard public works contracts in India runs for:

    A6 months from award of contract
    B12 months from virtual/practical completion of the work
    C24 months from the date of contract signing
    D36 months from first beneficial use of the structure

    Answer: B. 12 months from virtual/practical completion of the work

    Explanation: DLP = 12 months from Virtual Completion Certificate (VCC) date — the contractor must rectify all defects notified during this period at their own cost. After satisfactory DLP, the Final Completion Certificate is issued and security deposit is released. FIDIC recommends 12 months; varies with contract type.

  22. 22
    PYQ/PYQ-PatternMEDIUM

    For an activity, ES=2, LS=3, EF=7, LF=8. Total float is

    A2 days
    B5 days
    C3 days
    D1 days

    Answer: D. 1 days

    Explanation: Total float (TF) = LS - ES = LF - EF, where LS = Latest allowable Start, ES = Earliest possible Start, LF = Latest allowable Finish, EF = Earliest possible Finish. TF = 0 implies a critical activity (on the critical path); any delay directly delays project completion. Free float = min(ES_successors) - EF of that activity. Total float = LS-ES = LF-EF = 1 days.

  23. 23
    ScaffoldingMEDIUM

    An independent scaffold (freestanding scaffold) differs from a putlog scaffold in that:

    AIndependent scaffold is supported by the building wall at all levels
    BIndependent scaffold has two rows of standards and does not rely on the building for support
    CIndependent scaffold is used only for painting and finishing work
    DIndependent scaffold cannot exceed 5 m in height

    Answer: B. Independent scaffold has two rows of standards and does not rely on the building for support

    Explanation: Putlog scaffold: one row of standards + putlogs projecting into the wall (needs to lean on building). Independent scaffold: two parallel rows of standards, fully self-supporting — used when wall cannot be disturbed (renovation, repairs) or for multi-storey work. Independent is stronger and safer.

  24. 24
    PERTMEDIUM

    In PERT analysis, individual activity durations are assumed to follow a probability distribution because:

    ANormal distribution best fits all construction activities
    BBeta distribution is bounded (has minimum and maximum values), suitable for activity durations
    CPoisson distribution applies to random events on construction sites
    DExponential distribution models the decay of activity uncertainty over time

    Answer: B. Beta distribution is bounded (has minimum and maximum values), suitable for activity durations

    Explanation: PERT uses the Beta distribution because activity durations are bounded: they cannot be negative and have a definite maximum. Beta is flexible — it can be symmetric or skewed — and requires only three time estimates (a, m, b). The project duration approximates a normal distribution via CLT.

  25. 25
    PYQ/PYQ-PatternMEDIUM

    Contingencies in an estimate are provided for

    AUnforeseen minor expenses
    BTax only
    CDepreciation only
    DContractor profit only

    Answer: A. Unforeseen minor expenses

    Explanation: Contingencies cover small unforeseen items not specifically measured.

  26. 26
    Original practiceMEDIUM

    A detailed estimate is prepared from

    AOnly soil colour
    BWorking drawings and specifications
    COnly rough guess
    DOnly rainfall data

    Answer: B. Working drawings and specifications

    Explanation: Detailed estimate is quantity take-off based on drawings, rates and specifications.

  27. 27
    Critical ActivityMEDIUM

    In a CPM network, a critical activity is one with:

    AMaximum resource requirement
    BZero total float
    CMaximum duration among all activities
    DLongest predecessor chain

    Answer: B. Zero total float

    Explanation: Critical activities lie on the critical path — any delay increases project duration. They have zero total float (TF = LS − ES = LF − EF = 0). Non-critical activities have positive TF and can be delayed within limits without delaying the project.

  28. 28
    Quality ControlMEDIUM

    Acceptance sampling in construction quality control involves:

    ATesting every unit in every batch delivered to site
    BAccepting or rejecting an entire lot based on results from a random sample
    CDetermining the characteristic compressive strength of concrete only
    DNon-destructive testing of structural elements in service

    Answer: B. Accepting or rejecting an entire lot based on results from a random sample

    Explanation: Acceptance sampling (IS 2500) is a statistical QC technique: a sample is drawn from a lot, tested against AQL (Acceptable Quality Level), and the decision to accept/reject the whole lot is made. It balances inspection cost against risk of accepting defective material.

  29. 29
    Original practiceMEDIUM

    In long wall-short wall method, length of long wall is measured

    AOut-to-out
    BIn-to-in
    CCentre-to-centre only
    DAt plinth only

    Answer: A. Out-to-out

    Explanation: Long walls are measured out-to-out and short walls in-to-in.

  30. 30
    Earned ValueMEDIUM

    During an JE solution review on Earned Value, what is the safest statement about cost and schedule performance? Avoid the common trap that earned value uses only rainfall.

    Aearned value compares planned value, earned value and actual cost
    Bearned value uses only rainfall
    Cschedule variance is always zero
    Dactual cost is never recorded

    Answer: A. earned value compares planned value, earned value and actual cost

    Explanation: EVM integrates scope, cost and schedule progress. Correct option: A.

  31. 31
    Performance BondHARD

    In a CPWD (Central Public Works Department) contract, the performance security (security deposit) withheld from running bills is typically:

    A1–2% per bill until 10% of contract value is retained
    B5% deducted from each running bill until 5% of contract value is accumulated
    C10% of each running bill until 15% of contract value is accumulated
    D2.5% per bill until full contract amount is paid

    Answer: B. 5% deducted from each running bill until 5% of contract value is accumulated

    Explanation: CPWD GCC: security deposit = 5% of contract value. Recovered at 5% per running bill until the full 5% is accumulated. Also accepted as Bank Guarantee or FDR upfront. Released after successful DLP completion. FIDIC contracts typically require 10%; World Bank projects may require higher depending on risk profile.

  32. 32
    Construction Materials, Practices, Planning and ManagementHARD

    The critical path in a CPM network is the path with:

    Amaximum duration and zero total float
    Bmaximum number of activities only
    Cminimum cost only
    Dminimum duration and maximum float

    Answer: A. maximum duration and zero total float

    Explanation: Critical activities have zero total float and the critical path governs project completion time.

  33. 33
    Construction ManagementMEDIUM

    While submitting a tender, the amount a contractor deposits with the department as a guarantee of the tender is known as

    Abank guarantee
    Bearnest money
    Csecurity deposit
    Dcaution money

    Answer: B. earnest money

    Explanation: Tender security deposited with department is earnest money.

  34. 34
    Construction ManagementMEDIUM

    The critical path

    Ais always the longest
    Bis always the shortest
    Cmay be longer
    Dmay be shortest

    Answer: A. is always the longest

    Explanation: Critical path is the longest path in project network.

  35. 35
    Safety ManagementMEDIUM

    Which of the following about construction site hazard control is correct?

    Ahazards cannot be identified before work
    Bsafety is considered only after accidents
    Crisk assessment and PPE are part of safety planning
    DPPE replaces structural design

    Answer: C. risk assessment and PPE are part of safety planning

    Explanation: Construction safety requires proactive planning. Correct option: C.