Civil Engineering MCQAE Level Civil Engineering
If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Construction ManagementPYQ/PYQ-PatternMEDIUM
Choose the correct answer
A
Rs. 12500
B
Rs. 25000
C
Rs. 50000
D
Rs. 5005
Correct Answer
B. Rs. 25000
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Bill of quantities amount = measured quantity x unit rate (Rs.). In building estimation, cost = measured volume/area x analysis-of-rates unit cost. The abstract of cost aggregates all item amounts to give project total cost. Add GST and contractor overhead/profit to arrive at the contract (tender) value. Amount=quantity×rate=5×5000=Rs. 25000.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.