Civil Engineering MCQAE Level Civil Engineering
A detailed estimate is prepared from
Construction ManagementOriginal practiceMEDIUM
Choose the correct answer
A
Only soil colour
B
Working drawings and specifications
C
Only rough guess
D
Only rainfall data
Correct Answer
B. Working drawings and specifications
Why is this the answer?
Detailed estimate is quantity take-off based on drawings, rates and specifications.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.