Civil Engineering MCQAE Level Civil Engineering

The defects liability period (DLP) in most standard public works contracts in India runs for:

Construction ManagementContract ManagementMEDIUM

Choose the correct answer

A

6 months from award of contract

B

12 months from virtual/practical completion of the work

C

24 months from the date of contract signing

D

36 months from first beneficial use of the structure

Correct Answer

B. 12 months from virtual/practical completion of the work

Why is this the answer?

DLP = 12 months from Virtual Completion Certificate (VCC) date — the contractor must rectify all defects notified during this period at their own cost. After satisfactory DLP, the Final Completion Certificate is issued and security deposit is released. FIDIC recommends 12 months; varies with contract type.

Related Construction Management MCQs

More solved Construction Management questions for AE/JE Civil Engineering exams.

View all Construction Management MCQs →

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account