Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
Construction ManagementTender DocumentsMEDIUM
Choose the correct answer
A
Notice Inviting Tender (NIT)
B
Bill of Quantities (BOQ)
C
Letter of Acceptance (LOA)
D
General Conditions of Contract (GCC)
Correct Answer
C. Letter of Acceptance (LOA)
Why is this the answer?
NIT, BOQ, GCC, drawings and technical specifications are all tender documents issued to bidders before bid submission. LOA is sent to the successful bidder after evaluation to formally accept their offer — it is a post-tender document that converts the accepted bid into a contract.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
- One face of a wall 5 m by 3 m is to be plastered. Plastering area is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.