In rate analysis, contractor’s profit is commonly added as a percentage of
Construction ManagementGeneralMEDIUM
Choose the correct answer
A
only cement weight
B
only water charges
C
cost of materials, labour, equipment and overheads
D
only salvage value
Correct Answer
C. cost of materials, labour, equipment and overheads
Why is this the answer?
Contractor’s profit is added over the estimated cost components.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- One face of a wall 5 m by 3 m is to be plastered. Plastering area is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.