An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days and crash cost Rs.14,000. The cost slope is:

Construction ManagementProject CrashingMEDIUM

Choose the correct answer

A

Rs. 1,000/day

B

Rs. 2,000/day

C

Rs. 4,000/day

D

Rs. 6,000/day

Correct Answer

B. Rs. 2,000/day

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Cost slope = (Crash cost − Normal cost)/(Normal duration − Crash duration) = (14,000 − 8,000)/(10 − 7) = 6,000/3 = Rs. 2,000/day. Lower cost slope = cheaper to crash; crash this activity first in network crashing.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account