An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days and crash cost Rs.14,000. The cost slope is:
Construction ManagementProject CrashingMEDIUM
Choose the correct answer
A
Rs. 1,000/day
B
Rs. 2,000/day
C
Rs. 4,000/day
D
Rs. 6,000/day
Correct Answer
B. Rs. 2,000/day
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Cost slope = (Crash cost − Normal cost)/(Normal duration − Crash duration) = (14,000 − 8,000)/(10 − 7) = 6,000/3 = Rs. 2,000/day. Lower cost slope = cheaper to crash; crash this activity first in network crashing.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.