An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days and crash cost Rs.14,000. The cost slope is:

Construction ManagementProject CrashingMEDIUM

Choose the correct answer

A

Rs. 1,000/day

B

Rs. 2,000/day

C

Rs. 4,000/day

D

Rs. 6,000/day

Correct Answer

B. Rs. 2,000/day

Why is this the answer?

Cost slope = (Crash cost − Normal cost)/(Normal duration − Crash duration) = (14,000 − 8,000)/(10 − 7) = 6,000/3 = Rs. 2,000/day. Lower cost slope = cheaper to crash; crash this activity first in network crashing.