A revised estimate is prepared when
Construction ManagementGeneralMEDIUM
Choose the correct answer
A
only measurement book is lost
B
sanctioned estimate is likely to be exceeded beyond permissible limit
C
no design change occurs
D
work is completed exactly at original amount
Correct Answer
B. sanctioned estimate is likely to be exceeded beyond permissible limit
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Revised estimate is needed for material changes or cost escalation beyond allowed limits.