A revised estimate is prepared when

Construction ManagementGeneralMEDIUM

Choose the correct answer

A

only measurement book is lost

B

sanctioned estimate is likely to be exceeded beyond permissible limit

C

no design change occurs

D

work is completed exactly at original amount

Correct Answer

B. sanctioned estimate is likely to be exceeded beyond permissible limit

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Revised estimate is needed for material changes or cost escalation beyond allowed limits.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account