Civil Engineering MCQAE Level Civil Engineering
A revised estimate is prepared when
Construction ManagementGeneralMEDIUM
Choose the correct answer
A
only measurement book is lost
B
sanctioned estimate is likely to be exceeded beyond permissible limit
C
no design change occurs
D
work is completed exactly at original amount
Correct Answer
B. sanctioned estimate is likely to be exceeded beyond permissible limit
Why is this the answer?
Revised estimate is needed for material changes or cost escalation beyond allowed limits.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- One face of a wall 5 m by 3 m is to be plastered. Plastering area is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.