Civil Engineering MCQAE Level Civil Engineering

For an activity, ES=2, LS=3, EF=7, LF=8. Total float is

Construction ManagementPYQ/PYQ-PatternMEDIUM

Choose the correct answer

A

2 days

B

5 days

C

3 days

D

1 days

Correct Answer

D. 1 days

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Total float (TF) = LS - ES = LF - EF, where LS = Latest allowable Start, ES = Earliest possible Start, LF = Latest allowable Finish, EF = Earliest possible Finish. TF = 0 implies a critical activity (on the critical path); any delay directly delays project completion. Free float = min(ES_successors) - EF of that activity. Total float = LS-ES = LF-EF = 1 days.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account