For an activity, ES=2, LS=3, EF=7, LF=8. Total float is
Construction ManagementPYQ/PYQ-PatternMEDIUM
Choose the correct answer
A
2 days
B
5 days
C
3 days
D
1 days
Correct Answer
D. 1 days
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Total float (TF) = LS - ES = LF - EF, where LS = Latest allowable Start, ES = Earliest possible Start, LF = Latest allowable Finish, EF = Earliest possible Finish. TF = 0 implies a critical activity (on the critical path); any delay directly delays project completion. Free float = min(ES_successors) - EF of that activity. Total float = LS-ES = LF-EF = 1 days.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.