Contingencies in an estimate are provided for
Construction ManagementPYQ/PYQ-PatternMEDIUM
Choose the correct answer
A
Unforeseen minor expenses
B
Tax only
C
Depreciation only
D
Contractor profit only
Correct Answer
A. Unforeseen minor expenses
Why is this the answer?
Contingencies cover small unforeseen items not specifically measured.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.