A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes. Working at 50 productive minutes per hour, the output per hour is:
Construction ManagementConstruction EquipmentMEDIUM
Choose the correct answer
A
5.0 m³/hr
B
6.25 m³/hr
C
8.33 m³/hr
D
10.0 m³/hr
Correct Answer
C. 8.33 m³/hr
Why is this the answer?
Productive cycles/hr = 50 min ÷ 3 min = 16.67 cycles. Output = 16.67 × 0.5 m³ = 8.33 m³/hr. Efficiency factor accounts for changeover, setup and minor delays; a 50/60 ratio (83%) is standard for batching plants.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
- One face of a wall 5 m by 3 m is to be plastered. Plastering area is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.