A project has SPI (Schedule Performance Index) = 0.85. This indicates that the project is:

Construction ManagementEarned ValueMEDIUM

Choose the correct answer

A

15% ahead of schedule

B

Behind schedule — earning only 85 paise of work for every rupee of planned work

C

15% over budget

D

85% physically complete

Correct Answer

B. Behind schedule — earning only 85 paise of work for every rupee of planned work

Why is this the answer?

SPI = EV/PV. SPI < 1 means project is behind schedule (earning less value than planned). SPI = 0.85 means for every Rs.100 of work planned, only Rs.85 worth is actually accomplished. CPI = EV/AC measures cost performance. SPI > 1 = ahead of schedule; SPI < 1 = behind.

Related Construction Management MCQs

More solved Construction Management questions for AE/JE Civil Engineering exams.

View all Construction Management MCQs →

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account