A project has SPI (Schedule Performance Index) = 0.85. This indicates that the project is:
Construction ManagementEarned ValueMEDIUM
Choose the correct answer
A
15% ahead of schedule
B
Behind schedule — earning only 85 paise of work for every rupee of planned work
C
15% over budget
D
85% physically complete
Correct Answer
B. Behind schedule — earning only 85 paise of work for every rupee of planned work
Why is this the answer?
SPI = EV/PV. SPI < 1 means project is behind schedule (earning less value than planned). SPI = 0.85 means for every Rs.100 of work planned, only Rs.85 worth is actually accomplished. CPI = EV/AC measures cost performance. SPI > 1 = ahead of schedule; SPI < 1 = behind.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is