During an JE solution review on Earned Value, what is the safest statement about cost and schedule performance? Avoid the common trap that earned value uses only rainfall.
Construction ManagementEarned ValueMEDIUM
Choose the correct answer
A
earned value compares planned value, earned value and actual cost
B
earned value uses only rainfall
C
schedule variance is always zero
D
actual cost is never recorded
Correct Answer
A. earned value compares planned value, earned value and actual cost
Why is this the answer?
EVM integrates scope, cost and schedule progress. Correct option: A.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Practice more Civil Engineering questions
This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.