Civil Engineering MCQJE Level Civil Engineering

During an JE solution review on Earned Value, what is the safest statement about cost and schedule performance? Avoid the common trap that earned value uses only rainfall.

Construction ManagementEarned ValueMEDIUM

Choose the correct answer

A

earned value compares planned value, earned value and actual cost

B

earned value uses only rainfall

C

schedule variance is always zero

D

actual cost is never recorded

Correct Answer

A. earned value compares planned value, earned value and actual cost

Why is this the answer?

EVM integrates scope, cost and schedule progress. Correct option: A.