The critical path in a CPM network is the path with:
Construction ManagementConstruction Materials, Practices, Planning and ManagementHARD
Choose the correct answer
A
maximum duration and zero total float
B
maximum number of activities only
C
minimum cost only
D
minimum duration and maximum float
Correct Answer
A. maximum duration and zero total float
Why is this the answer?
Critical activities have zero total float and the critical path governs project completion time.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.