The critical path in a CPM network is the path with:

Construction ManagementConstruction Materials, Practices, Planning and ManagementHARD

Choose the correct answer

A

maximum duration and zero total float

B

maximum number of activities only

C

minimum cost only

D

minimum duration and maximum float

Correct Answer

A. maximum duration and zero total float

Why is this the answer?

Critical activities have zero total float and the critical path governs project completion time.