The process of determining present worth of a property is called:
Construction ManagementEstimating, Costing and Construction ManagementEASY
Choose the correct answer
A
Tendering
B
Valuation
C
Indenting
D
Gauging
Correct Answer
B. Valuation
Why is this the answer?
Valuation estimates the current monetary worth of a property or asset.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- One face of a wall 5 m by 3 m is to be plastered. Plastering area is
Practice more Civil Engineering questions
This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.