Civil Engineering MCQAE Level Civil Engineering

Independent float of an activity is the maximum delay that can be used without affecting:

Construction ManagementNetwork AnalysisMEDIUM

Choose the correct answer

A

Only the early start of successor activities

B

Either the late finish of predecessor or early start of successor activities

C

Only the total float of preceding activities

D

The critical path length of the project

Correct Answer

B. Either the late finish of predecessor or early start of successor activities

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Independent float = max(0, ES_successor − LF_predecessor − Duration). It can be consumed without affecting either predecessors or successors. IF ≤ Free Float ≤ Total Float. IF is always ≥ 0 and often = 0. It represents truly 'safe' delay time for an activity.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account