Civil Engineering MCQAE Level Civil Engineering

Independent float of an activity is the maximum delay that can be used without affecting:

Construction ManagementNetwork AnalysisMEDIUM

Choose the correct answer

A

The early start of successor activities

B

The early start of successor activities and the late finish of predecessor activities

C

The total float of preceding activities

D

The critical path length of the project

Correct Answer

B. The early start of successor activities and the late finish of predecessor activities

Why is this the answer?

Independent float is the amount of time an activity can be delayed without affecting the early start of any successor activity or the late finish of any predecessor activity. It is calculated as: IF = ES_successor - LF_predecessor - Duration_activity (if negative, IF = 0).

Related Construction Management MCQs

More solved Construction Management questions for AE/JE Civil Engineering exams.

View all Construction Management MCQs →

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account