As per IS 456:2000, the minimum number of samples of concrete to be taken per day's pour for a structure is:
Construction ManagementQuality ControlMEDIUM
Choose the correct answer
A
1 sample per 5 m³ — no minimum frequency
B
1 sample per 50 m³ but not less than 4 samples per day of pour
C
2 samples per day regardless of volume
D
1 sample per batch regardless of volume
Correct Answer
B. 1 sample per 50 m³ but not less than 4 samples per day of pour
Why is this the answer?
IS 456:2000 Cl. 15.2.2: Minimum frequency of sampling = 1 sample per 50 m³ or per day of pour, whichever requires more samples, but not less than 4 samples for a day's pour when volume > 30 m³. Each sample = 3 cubes (tested at 7 days, 28 days). This ensures statistical validity.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.