In the PERT technique, the critical path has slack equal to

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

always zero

B

positive value

C

negative value

D

zero

Correct Answer

D. zero

Why is this the answer?

In PERT/CPM, the critical path is defined as the path with zero slack (or minimum slack in a network). While negative slack can exist in constrained projects, the standard definition of the critical path is zero slack.