Civil Engineering MCQAE Level Civil Engineering

In the PERT technique, the critical path has slack equal to

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

always zero

B

positive value

C

negative value

D

zero or negative value

Correct Answer

D. zero or negative value

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PERT critical path has zero or negative slack.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap