In the PERT technique, the critical path has slack equal to
Construction ManagementConstruction ManagementMEDIUM
Choose the correct answer
A
always zero
B
positive value
C
negative value
D
zero
Correct Answer
D. zero
Why is this the answer?
In PERT/CPM, the critical path is defined as the path with zero slack (or minimum slack in a network). While negative slack can exist in constrained projects, the standard definition of the critical path is zero slack.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Practice more Civil Engineering questions
This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.