Civil Engineering MCQAE Level Civil Engineering
A 'revised estimate' in public works is prepared when the sanctioned amount is likely to be exceeded by more than:
Construction ManagementEstimate TypesMEDIUM
Choose the correct answer
A
2.5%
B
5%
C
10%
D
15%
Correct Answer
B. 5%
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
As per general financial rules, a revised estimate must be prepared when the probable cost of the work exceeds the sanctioned amount by more than 5%. It must be submitted for fresh approval before expenditure exceeds sanction. A supplementary estimate is prepared for additional work not included in original scope.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.