A 'revised estimate' in public works is prepared when the sanctioned amount is likely to be exceeded by more than:

Construction ManagementEstimate TypesMEDIUM

Choose the correct answer

A

2.5%

B

5%

C

10%

D

15%

Correct Answer

B. 5%

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

As per general financial rules, a revised estimate must be prepared when the probable cost of the work exceeds the sanctioned amount by more than 5%. It must be submitted for fresh approval before expenditure exceeds sanction. A supplementary estimate is prepared for additional work not included in original scope.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account