A 'revised estimate' in public works is prepared when the sanctioned amount is likely to be exceeded by more than:

Construction ManagementEstimate TypesMEDIUM

Choose the correct answer

A

2.5%

B

5%

C

10%

D

15%

Correct Answer

B. 5%

Why is this the answer?

As per general financial rules, a revised estimate must be prepared when the probable cost of the work exceeds the sanctioned amount by more than 5%. It must be submitted for fresh approval before expenditure exceeds sanction. A supplementary estimate is prepared for additional work not included in original scope.