Civil Engineering MCQAE Level Civil Engineering
The critical path
Construction ManagementConstruction ManagementMEDIUM
Choose the correct answer
A
is always the longest
B
is always the shortest
C
may be longer
D
may be shortest
Correct Answer
A. is always the longest
Why is this the answer?
Critical path is the longest path in project network.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Practice more Civil Engineering questions
This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.