The critical path

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

is always the longest

B

is always the shortest

C

may be longer

D

may be shortest

Correct Answer

A. is always the longest

Why is this the answer?

Critical path is the longest path in project network.