In a CPM network, a critical activity is one with:

Construction ManagementCritical ActivityMEDIUM

Choose the correct answer

A

Maximum resource requirement

B

Zero total float

C

Maximum duration among all activities

D

Longest predecessor chain

Correct Answer

B. Zero total float

Why is this the answer?

Critical activities lie on the critical path — any delay increases project duration. They have zero total float (TF = LS − ES = LF − EF = 0). Non-critical activities have positive TF and can be delayed within limits without delaying the project.