In a CPM network, a critical activity is one with:
Construction ManagementCritical ActivityMEDIUM
Choose the correct answer
A
Maximum resource requirement
B
Zero total float
C
Maximum duration among all activities
D
Longest predecessor chain
Correct Answer
B. Zero total float
Why is this the answer?
Critical activities lie on the critical path — any delay increases project duration. They have zero total float (TF = LS − ES = LF − EF = 0). Non-critical activities have positive TF and can be delayed within limits without delaying the project.
Related Construction Management MCQs
More solved Construction Management questions for AE/JE Civil Engineering exams.
- An activity has normal duration 10 days, normal cost Rs.8,000, crash duration 7 days...
- Which of the following is issued AFTER a contract is awarded and is NOT a tender document?
- In a lump sum contract, cost overruns due to unforeseen site conditions are borne by:
- A concrete batching plant produces 0.5 m³ per batch with a cycle time of 3 minutes....
- A brick wall is 5 m long, 4 m high and 0.35 m thick. Quantity of brick masonry is
- If concrete quantity is 5 m³ and rate is Rs. 5000/m³, amount is
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.