In a CPM network, a critical activity is one with:

Construction ManagementCritical ActivityMEDIUM

Choose the correct answer

A

Maximum resource requirement

B

Zero total float

C

Maximum duration among all activities

D

Longest predecessor chain

Correct Answer

B. Zero total float

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Critical activities lie on the critical path — any delay increases project duration. They have zero total float (TF = LS − ES = LF − EF = 0). Non-critical activities have positive TF and can be delayed within limits without delaying the project.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account