Civil Engineering MCQAE Level Civil Engineering

While submitting a tender, the amount a contractor deposits with the department as a guarantee of the tender is known as

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

bank guarantee

B

earnest money

C

security deposit

D

caution money

Correct Answer

B. earnest money

Why is this the answer?

Tender security deposited with department is earnest money.