Civil Engineering MCQAE Level Civil Engineering

As per IS 456:2000, the minimum period after casting before formwork (shuttering) of vertical faces of columns and walls may be removed is:

Construction ManagementFormwork StrikingMEDIUM

Choose the correct answer

A

6 hours

B

16–24 hours

C

3 days

D

7 days

Correct Answer

B. 16–24 hours

Why is this the answer?

IS 456:2000 Table 5 (Stripping times): Vertical faces of beams and columns = 16–24 hrs. Soffit of slabs (with props) = 3 days. Soffit of beams (props remaining) = 7 days. Removal of props for beams spanning ≤6 m = 14 days. Earlier stripping risks cold joint and surface damage.

Related Construction Management MCQs

More solved Construction Management questions for AE/JE Civil Engineering exams.

View all Construction Management MCQs →

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account