In PERT analysis, individual activity durations are assumed to follow a probability distribution because:

Construction ManagementPERTMEDIUM

Choose the correct answer

A

Normal distribution best fits all construction activities

B

Beta distribution is bounded (has minimum and maximum values), suitable for activity durations

C

Poisson distribution applies to random events on construction sites

D

Exponential distribution models the decay of activity uncertainty over time

Correct Answer

B. Beta distribution is bounded (has minimum and maximum values), suitable for activity durations

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PERT uses the Beta distribution because activity durations are bounded: they cannot be negative and have a definite maximum. Beta is flexible — it can be symmetric or skewed — and requires only three time estimates (a, m, b). The project duration approximates a normal distribution via CLT.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap