Practice SetEstimation and Costing

Estimation and Costing MCQ Practice Set — 26 Questions with Answers

26 exam-oriented Estimation and Costing multiple-choice questions with the correct answer and a clear explanation for each. Frequently asked in AE Level Civil Engineering, JE Level Civil Engineering. Solve the full set below for free — no login required.

  1. 1
    Plinth Area Rate MethodMEDIUM

    The plinth area rate method for estimating building cost is based on:

    AVolume of the building
    BTotal area covered at the plinth level (floor area) multiplied by the plinth area rate per m2 for that type of construction
    CLength of external walls only
    DNumber of rooms

    Answer: B. Total area covered at the plinth level (floor area) multiplied by the plinth area rate per m2 for that type of construction

    Explanation: Plinth area = area of building at plinth level (excluding walls, including internal spaces). Plinth area rate (PAR) is obtained from similar buildings in the locality, adjusted for finishes and current market rates. This is a rough method for preliminary estimate with accuracy of +-15 to +-20%.

  2. 2
    Estimating, Costing and Construction ManagementHARD

    For 1:4:8 concrete, total proportion is:

    A8
    B4
    C12
    D13

    Answer: D. 13

    Explanation: Concrete mix 1:4:8 means cement : fine aggregate (sand) : coarse aggregate (gravel) in proportions 1:4:8. Total parts = 1 + 4 + 8 = 13. Each ingredient's fraction: cement = 1/13, fine agg = 4/13, coarse agg = 8/13. Nominal mixes (IS 456): M10 = 1:3:6, M15 = 1:2:4, M20 = 1:1.5:3, M25 = 1:1:2.

  3. 3
    Estimating, Costing and Construction ManagementEASY

    Sinking fund method of depreciation considers:

    AOnly physical wear
    BNo salvage value at all
    COnly arithmetic average cost
    DCompound interest on annual deposits

    Answer: D. Compound interest on annual deposits

    Explanation: Equal annual deposits earn interest and accumulate to replace the asset.

  4. 4
    ContingenciesMEDIUM

    Which of the following about allowance for unforeseen minor items in civil engineering is correct?

    Acontingency means contractor profit only
    Bit replaces detailed quantities
    Cit is always negative
    Da percentage provision is included in estimates

    Answer: D. a percentage provision is included in estimates

    Explanation: Contingencies cover minor unpredictable costs. Correct option: D.

  5. 5
    PERT Beta DistributionMEDIUM

    In PERT, the expected duration te of an activity with optimistic time a, most likely time m, and pessimistic time b (beta distribution) is:

    Ate = (a + m + b) / 3
    Bte = (a + 4m + b) / 6
    Cte = (a + b) / 2
    Dte = m only

    Answer: B. te = (a + 4m + b) / 6

    Explanation: PERT: te = (a + 4m + b)/6; variance sigma^2 = ((b-a)/6)^2. Expected project duration = sum of te on critical path. Variance of project = sum of variances on critical path. Project completion time follows normal distribution. Probability of completing by time T: Z = (T - sum_te) / sqrt(sum_sigma^2).

  6. 6
    Resource LevelingMEDIUM

    Resource leveling in project scheduling aims to:

    AAlways reduce project duration
    BReduce peak resource demands and smooth resource utilization by shifting non-critical activities within their float, often at the expense of project duration
    CIncrease resource peaks
    DRemove all float from the schedule

    Answer: B. Reduce peak resource demands and smooth resource utilization by shifting non-critical activities within their float, often at the expense of project duration

    Explanation: Resource leveling: shifts activities (within their float for non-critical; allows duration extension for critical) to reduce resource peaks. Heuristic methods: minimum float priority (critical activities done first), minimum slack, most resources. May extend project duration. Resource smoothing: same as leveling but does not extend project duration.

  7. 7
    Detailed Project EstimateMEDIUM

    A Detailed Project Estimate (DPE) is prepared from:

    AApproximate dimensions only
    BCompleted working drawings, specifications, and detailed rate analyses for every item of work
    CThumb rules only
    DPlinth area method

    Answer: B. Completed working drawings, specifications, and detailed rate analyses for every item of work

    Explanation: DPE (most accurate estimate, +-5% accuracy): based on complete working drawings and specifications. Compute quantities item-by-item per IS 1200 (measurement), analyze rates per DSR/market rates, add contingency and supervision charges. DPE is the basis for tender documents and project sanction. Requires complete design.

  8. 8
    CPM Critical PathMEDIUM

    In the Critical Path Method (CPM), the total float of an activity is:

    AThe amount of time by which the activity duration can be reduced
    BThe maximum time the activity can be delayed without delaying the overall project completion (= LFT - EST - Duration)
    CThe free float minus the independent float
    DThe sum of all activity durations

    Answer: B. The maximum time the activity can be delayed without delaying the overall project completion (= LFT - EST - Duration)

    Explanation: Total float TF = LFT - EST - D = LST - EST = LFT - EFT (where LFT = latest finish time, EST = earliest start time, D = duration). Critical activities have TF = 0. Free float = EFT(next activity) - EFT(current). Independent float = EST(next) - LFT(preceding) - D (can be negative). Critical path = longest duration path with TF = 0.

  9. 9
    Arch CenteringMEDIUM

    The effective span of an arch in masonry is measured as:

    ADistance between outer faces of abutments
    BClear span between inner faces of supports plus the depth of skewbacks (bearing on abutments), typically = clear span for semicircular arches
    CHeight of arch only
    DWidth of arch barrel

    Answer: B. Clear span between inner faces of supports plus the depth of skewbacks (bearing on abutments), typically = clear span for semicircular arches

    Explanation: Arch effective span = clear span between faces of supports (for flat or segmental arches with no defined skewback). For semicircular arch: effective span = clear span. Arch masonry is measured as the volume of masonry in the arch ring (length x width x thickness of ring). Centring (temporary support during construction) is measured separately.

  10. 10
    Cement Mortar Mix VolumeMEDIUM

    If a cement mortar mix is 1:4 (cement:sand) by volume, and wet mortar shrinks approximately 33% after setting, the dry volume of materials required per m3 of finished mortar is:

    A1 m3 cement + 4 m3 sand
    B1.5 m3 of mixed materials (0.3 m3 cement + 1.2 m3 sand in dry volume)
    CExactly 1 m3 of sand + 0.25 m3 cement
    D5 bags cement + 1 m3 sand

    Answer: B. 1.5 m3 of mixed materials (0.3 m3 cement + 1.2 m3 sand in dry volume)

    Explanation: Wet to dry conversion: 1 m3 wet mortar = 1.3 to 1.5 m3 dry materials (due to bulking and water absorption). For 1:4 mix: dry materials = 1.5 m3 total; cement = 1.5/5 = 0.3 m3 = about 8.6 bags (50 kg, 0.035 m3/bag); sand = 1.2 m3. Actual values depend on bulking of sand.

  11. 11
    Painting MeasurementMEDIUM

    Painting of walls and ceilings is measured in:

    ACubic metres
    BSquare metres of surface area, with number of coats specified in the item description
    CRunning metres of length only
    DNumber of paint tins used

    Answer: B. Square metres of surface area, with number of coats specified in the item description

    Explanation: Painting: measured in m2 of surface area. Rates are specified per m2 for a stated number of coats (e.g., 2 coats priming + 2 coats enamel). For cornices, bands: per running metre. For grills, railings with complex geometry: measured flat face area or as multiple of equivalent flat area. Quantity = area x rate.

  12. 12
    Plastering QuantityMEDIUM

    For computing the quantity of plastering on walls, the area measured is:

    AOnly external face area
    BNet wall face area (length x height), with deductions for openings (doors, windows) above a threshold area, and additions for reveals, jambs, and soffits of openings
    CGross area without any deduction
    DFloor area only

    Answer: B. Net wall face area (length x height), with deductions for openings (doors, windows) above a threshold area, and additions for reveals, jambs, and soffits of openings

    Explanation: CPWD plastering measurement: length x height (net area) minus openings > 0.5 m2 (some codes: > 0.1 m2). Additions: reveal (width x height of wall at door/window opening), sill (width x depth), lintels (soffit). Mortar quantity = (volume of plaster coat) / (1 - bulking factor). Typical plaster thickness: 12-18 mm (2 coats).

  13. 13
    Flooring Area MeasurementMEDIUM

    When computing the quantity of flooring in a room, the area is measured as:

    AExternal dimensions of walls only
    BClear floor area between walls (internal dimensions of the room), without deduction for columns or fixtures unless area of each column exceeds 0.1 m2
    CExternal area of the building
    DArea including the thickness of all walls

    Answer: B. Clear floor area between walls (internal dimensions of the room), without deduction for columns or fixtures unless area of each column exceeds 0.1 m2

    Explanation: CPWD measurement: flooring = net area between walls (internal dimensions). No deduction for areas < 0.04 m2; deductions for columns, pillars, piers > 0.04 m2. Skirting measured separately in running metres. Different rates for different flooring types (tiles, marble, mosaic, PCC, etc.).

  14. 14
    Overhead ChargesMEDIUM

    In rate analysis, overhead charges (establishment charges) typically include:

    ACost of raw materials
    BSalaries of office staff, rent of contractor office, electricity bills, insurance, and administrative expenses that cannot be directly attributed to a specific work item
    CLabour wages at site
    DPlant hire directly on site

    Answer: B. Salaries of office staff, rent of contractor office, electricity bills, insurance, and administrative expenses that cannot be directly attributed to a specific work item

    Explanation: Overheads: indirect costs not directly attributable to specific work items. Includes: contractor office expenses, engineer salaries, insurance, bonding, site supervision, quality control, accounting. As a percentage of direct cost: usually 10-15%. Plus profit margin: 5-10%. Together = 15-25% mark-up on direct cost.

  15. 15
    Lead and Lift EarthworkMEDIUM

    In earthwork estimation, "lead" refers to the horizontal distance of transport and "lift" refers to the vertical height of lifting. Which statement is correct?

    ALead is always 30 m; lift is always 1.5 m
    BLead and lift affect the rate of earth carriage; extra lead and lift beyond the standard lead (30 m) and lift (1.5 m) attract extra rate per unit distance/height in DSR
    CLead increases cost; lift decreases cost
    DLead and lift are irrelevant for manual labour

    Answer: B. Lead and lift affect the rate of earth carriage; extra lead and lift beyond the standard lead (30 m) and lift (1.5 m) attract extra rate per unit distance/height in DSR

    Explanation: DSR (Delhi Schedule of Rates) classifies earthwork into standard lead (30 m) and standard lift (1.5 m). For additional lead beyond 30 m: extra rate per 50 m lead (in graduated slabs). For additional lift beyond 1.5 m: extra rate per 1.5 m lift. Both affect the total earthwork carriage cost in highways and irrigation projects.

  16. 16
    ContingenciesMEDIUM

    Which of the following statements about allowance for unforeseen minor items is technically sound?

    Aa percentage provision is included in estimates
    Bcontingency means contractor profit only
    Cit replaces detailed quantities
    Dit is always negative

    Answer: A. a percentage provision is included in estimates

    Explanation: Contingencies cover minor unpredictable costs. Correct option: A.

  17. 17
    Highway Engineering, Estimating, Costing and ContractsHARD

    Lift in earthwork means:

    Awidth of trench
    Bvertical height through which earth is raised
    Chorizontal transport distance
    Ddensity of soil

    Answer: B. vertical height through which earth is raised

    Explanation: Lift is the vertical movement of excavated earth.

  18. 18
    Construction Materials, Practices, Planning and ManagementHARD

    In rate analysis, contractor's profit and overhead are generally added to:

    Aonly cement cost
    Bdirect cost of materials, labour, equipment and carriage
    Conly water charges
    Donly depreciation

    Answer: B. direct cost of materials, labour, equipment and carriage

    Explanation: Rate analysis builds item rates from direct costs and adds overheads and profit as per practice/specifications.

  19. 19
    Estimating, Costing and Construction ManagementEASY

    Plinth area estimate is obtained by multiplying plinth area by:

    ANumber of doors
    BPlinth area rate
    CExcavation depth
    DCarpet area only

    Answer: B. Plinth area rate

    Explanation: Approximate cost can be estimated using known plinth area rates for similar buildings.

  20. 20
    Estimating, Costing and Construction ManagementEASY

    For openings in masonry, no deduction is generally made when each opening area does not exceed:

    A0.1 square metre
    B1.0 square metre
    C0.5 square metre
    D2.0 square metre

    Answer: A. 0.1 square metre

    Explanation: Very small openings are often ignored as the labour of forming edges balances material saved.

  21. 21
    Estimating, Costing and Construction ManagementHARD

    If 1 bag cement occupies 0.0347 cubic metre, cement bags for 0.071 cubic metre cement are approximately:

    A0.50 bags
    B1.05 bags
    C2.05 bags
    D3.50 bags

    Answer: C. 2.05 bags

    Explanation: Number of bags = 0.071/0.0347, about 2.05.

  22. 22
    Estimating, Costing and Construction ManagementEASY

    In earthwork, lead refers to the:

    AHorizontal distance of transport
    BVertical height of lift
    CDepth of excavation
    DSide slope ratio

    Answer: A. Horizontal distance of transport

    Explanation: Lead is the average horizontal distance through which excavated material is carried.

  23. 23
    Estimation and CostingMEDIUM

    Generally the unit of measurement of partition wall is:

    Avolume
    Barea
    Clength
    Dnumber

    Answer: B. area

    Explanation: Partition walls are commonly measured by area when their thickness is small or standardized

  24. 24
    Estimation and CostingMEDIUM

    Working out the exact quantities of various items of work is known as

    Aestimating
    Bmensuration
    Cquantity surveying
    Dvaluation

    Answer: C. quantity surveying

    Explanation: Working out quantities for construction items is quantity surveying

  25. 25
    Estimation and CostingMEDIUM

    If the cross-sectional areas of an embankment at 30 m intervals are 20, 40, 60, 50 and 30 m² respectively, then the volume of the embankment by the prismoidal rule is

    A5300 m³
    B8300 m³
    C9300 m³
    D9400 m³

    Answer: A. 5300 m³

    Explanation: Prismoidal rule volume using given areas and spacing gives 5300 m3.

  26. 26
    Lead and LiftEASY

    For field interpretation of Lead and Lift, the issue is earthwork costing. What should be selected?

    Alead is cement setting time
    Bboth are ignored in earthwork rates
    Clead is horizontal transport distance and lift is vertical raising distance
    Dlift is aggregate size

    Answer: C. lead is horizontal transport distance and lift is vertical raising distance

    Explanation: Earthwork rates depend on transport and vertical movement. Correct option: C.