Civil Engineering MCQAE Level Civil Engineering
Which of the following about allowance for unforeseen minor items in civil engineering is correct?
Estimation and CostingContingenciesMEDIUM
Choose the correct answer
A
contingency means contractor profit only
B
it replaces detailed quantities
C
it is always negative
D
a percentage provision is included in estimates
Correct Answer
D. a percentage provision is included in estimates
Why is this the answer?
Contingencies cover minor unpredictable costs. Correct option: D.
Related Estimation and Costing MCQs
More solved Estimation and Costing questions for AE/JE Civil Engineering exams.
- The plinth area rate method for estimating building cost is based on:
- For 1:4:8 concrete, total proportion is:
- Sinking fund method of depreciation considers:
- In PERT, the expected duration te of an activity with optimistic time a, most likely...
- Resource leveling in project scheduling aims to:
- A Detailed Project Estimate (DPE) is prepared from:
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.