For field interpretation of Lead and Lift, the issue is earthwork costing. What should be selected?
Estimation and CostingLead and LiftEASY
Choose the correct answer
A
lead is cement setting time
B
both are ignored in earthwork rates
C
lead is horizontal transport distance and lift is vertical raising distance
D
lift is aggregate size
Correct Answer
C. lead is horizontal transport distance and lift is vertical raising distance
Why is this the answer?
Earthwork rates depend on transport and vertical movement. Correct option: C.
Related Estimation and Costing MCQs
More solved Estimation and Costing questions for AE/JE Civil Engineering exams.
- The plinth area rate method for estimating building cost is based on:
- For 1:4:8 concrete, total proportion is:
- Sinking fund method of depreciation considers:
- Which of the following about allowance for unforeseen minor items in civil engineering...
- In PERT, the expected duration te of an activity with optimistic time a, most likely...
- Resource leveling in project scheduling aims to:
Practice more Civil Engineering questions
This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.