For field interpretation of Lead and Lift, the issue is earthwork costing. What should be selected?

Estimation and CostingLead and LiftEASY

Choose the correct answer

A

lead is cement setting time

B

both are ignored in earthwork rates

C

lead is horizontal transport distance and lift is vertical raising distance

D

lift is aggregate size

Correct Answer

C. lead is horizontal transport distance and lift is vertical raising distance

Why is this the answer?

Earthwork rates depend on transport and vertical movement. Correct option: C.