Civil Engineering MCQAE Level Civil Engineering

Resource leveling in project scheduling aims to:

Estimation and CostingResource LevelingMEDIUM

Choose the correct answer

A

Always reduce project duration

B

Reduce peak resource demands and smooth resource utilization by shifting non-critical activities within their float, often at the expense of project duration

C

Increase resource peaks

D

Remove all float from the schedule

Correct Answer

B. Reduce peak resource demands and smooth resource utilization by shifting non-critical activities within their float, often at the expense of project duration

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Resource leveling: shifts activities (within their float for non-critical; allows duration extension for critical) to reduce resource peaks. Heuristic methods: minimum float priority (critical activities done first), minimum slack, most resources. May extend project duration. Resource smoothing: same as leveling but does not extend project duration.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account