If 1 bag cement occupies 0.0347 cubic metre, cement bags for 0.071 cubic metre cement are approximately:
Estimation and CostingEstimating, Costing and Construction ManagementHARD
Choose the correct answer
A
0.50 bags
B
1.05 bags
C
2.05 bags
D
3.50 bags
Correct Answer
C. 2.05 bags
Why is this the answer?
Number of bags = 0.071/0.0347, about 2.05.
Related Estimation and Costing MCQs
More solved Estimation and Costing questions for AE/JE Civil Engineering exams.
- The plinth area rate method for estimating building cost is based on:
- For 1:4:8 concrete, total proportion is:
- Sinking fund method of depreciation considers:
- Which of the following about allowance for unforeseen minor items in civil engineering...
- In PERT, the expected duration te of an activity with optimistic time a, most likely...
- Resource leveling in project scheduling aims to:
Practice more Civil Engineering questions
This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.