Civil Engineering MCQJE Level Civil Engineering
If 1 bag cement occupies 0.0347 cubic metre, cement bags for 0.071 cubic metre cement are approximately:
Estimation and CostingEstimating, Costing and Construction ManagementHARD
Choose the correct answer
A
0.50 bags
B
1.05 bags
C
2.05 bags
D
3.50 bags
Correct Answer
C. 2.05 bags
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Number of bags = 0.071/0.0347, about 2.05.