For 1:4:8 concrete, total proportion is:

Estimation and CostingEstimating, Costing and Construction ManagementHARD

Choose the correct answer

A

8

B

4

C

12

D

13

Correct Answer

D. 13

Why is this the answer?

Concrete mix 1:4:8 means cement : fine aggregate (sand) : coarse aggregate (gravel) in proportions 1:4:8. Total parts = 1 + 4 + 8 = 13. Each ingredient's fraction: cement = 1/13, fine agg = 4/13, coarse agg = 8/13. Nominal mixes (IS 456): M10 = 1:3:6, M15 = 1:2:4, M20 = 1:1.5:3, M25 = 1:1:2.