Civil Engineering MCQJE Level Civil Engineering
In earthwork, lead refers to the:
Estimation and CostingEstimating, Costing and Construction ManagementEASY
Choose the correct answer
A
Horizontal distance of transport
B
Vertical height of lift
C
Depth of excavation
D
Side slope ratio
Correct Answer
A. Horizontal distance of transport
Why is this the answer?
Lead is the average horizontal distance through which excavated material is carried.
Related Estimation and Costing MCQs
More solved Estimation and Costing questions for AE/JE Civil Engineering exams.
- The plinth area rate method for estimating building cost is based on:
- For 1:4:8 concrete, total proportion is:
- Sinking fund method of depreciation considers:
- Which of the following about allowance for unforeseen minor items in civil engineering...
- In PERT, the expected duration te of an activity with optimistic time a, most likely...
- Resource leveling in project scheduling aims to:
Practice more Civil Engineering questions
This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.