Civil Engineering MCQAE Level Civil Engineering

In the Critical Path Method (CPM), the total float of an activity is:

Estimation and CostingCPM Critical PathMEDIUM

Choose the correct answer

A

The amount of time by which the activity duration can be reduced

B

The maximum time the activity can be delayed without delaying the overall project completion (= LFT - EST - Duration)

C

The free float minus the independent float

D

The sum of all activity durations

Correct Answer

B. The maximum time the activity can be delayed without delaying the overall project completion (= LFT - EST - Duration)

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Total float TF = LFT - EST - D = LST - EST = LFT - EFT (where LFT = latest finish time, EST = earliest start time, D = duration). Critical activities have TF = 0. Free float = EFT(next activity) - EFT(current). Independent float = EST(next) - LFT(preceding) - D (can be negative). Critical path = longest duration path with TF = 0.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account