In rate analysis, contractor's profit and overhead are generally added to:

Estimation and CostingConstruction Materials, Practices, Planning and ManagementHARD

Choose the correct answer

A

only cement cost

B

direct cost of materials, labour, equipment and carriage

C

only water charges

D

only depreciation

Correct Answer

B. direct cost of materials, labour, equipment and carriage

Why is this the answer?

Rate analysis builds item rates from direct costs and adds overheads and profit as per practice/specifications.