Civil Engineering MCQAE Level Civil Engineering
In rate analysis, contractor's profit and overhead are generally added to:
Estimation and CostingConstruction Materials, Practices, Planning and ManagementHARD
Choose the correct answer
A
only cement cost
B
direct cost of materials, labour, equipment and carriage
C
only water charges
D
only depreciation
Correct Answer
B. direct cost of materials, labour, equipment and carriage
Why is this the answer?
Rate analysis builds item rates from direct costs and adds overheads and profit as per practice/specifications.
Related Estimation and Costing MCQs
More solved Estimation and Costing questions for AE/JE Civil Engineering exams.
- The plinth area rate method for estimating building cost is based on:
- For 1:4:8 concrete, total proportion is:
- Sinking fund method of depreciation considers:
- Which of the following about allowance for unforeseen minor items in civil engineering...
- In PERT, the expected duration te of an activity with optimistic time a, most likely...
- Resource leveling in project scheduling aims to:
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.