A Detailed Project Estimate (DPE) is prepared from:
Choose the correct answer
Approximate dimensions only
Completed working drawings, specifications, and detailed rate analyses for every item of work
Thumb rules only
Plinth area method
Correct Answer
B. Completed working drawings, specifications, and detailed rate analyses for every item of work
Why is this the answer?
DPE (most accurate estimate, +-5% accuracy): based on complete working drawings and specifications. Compute quantities item-by-item per IS 1200 (measurement), analyze rates per DSR/market rates, add contingency and supervision charges. DPE is the basis for tender documents and project sanction. Requires complete design.
Related Estimation and Costing MCQs
More solved Estimation and Costing questions for AE/JE Civil Engineering exams.
- The plinth area rate method for estimating building cost is based on:
- For 1:4:8 concrete, total proportion is:
- Sinking fund method of depreciation considers:
- Which of the following about allowance for unforeseen minor items in civil engineering...
- In PERT, the expected duration te of an activity with optimistic time a, most likely...
- Resource leveling in project scheduling aims to:
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.