Civil Engineering MCQAE Level Civil Engineering

If a cement mortar mix is 1:4 (cement:sand) by volume, and wet mortar shrinks approximately 33% after setting, the dry volume of materials required per m3 of finished mortar is:

Estimation and CostingCement Mortar Mix VolumeMEDIUM

Choose the correct answer

A

1 m3 cement + 4 m3 sand

B

1.5 m3 of mixed materials (0.3 m3 cement + 1.2 m3 sand in dry volume)

C

Exactly 1 m3 of sand + 0.25 m3 cement

D

5 bags cement + 1 m3 sand

Correct Answer

B. 1.5 m3 of mixed materials (0.3 m3 cement + 1.2 m3 sand in dry volume)

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Wet to dry conversion: 1 m3 wet mortar = 1.3 to 1.5 m3 dry materials (due to bulking and water absorption). For 1:4 mix: dry materials = 1.5 m3 total; cement = 1.5/5 = 0.3 m3 = about 8.6 bags (50 kg, 0.035 m3/bag); sand = 1.2 m3. Actual values depend on bulking of sand.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account