The 'prismoidal formula' for computing volume of earthwork between two cross-sections is:

SurveyingSurveyingMEDIUM

Choose the correct answer

A

V = (A1 + A2)/2 × L (average end area)

B

V = L/6 × (A1 + 4Am + A2) — prismoidal formula with mid-section area

C

V = L × Am only

D

V = L × (A1 × A2)^0.5

Correct Answer

B. V = L/6 × (A1 + 4Am + A2) — prismoidal formula with mid-section area

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Prismoidal formula: V = (L/6) × (A1 + 4Am + A2) where L = distance between sections, A1 and A2 = end areas, Am = mid-section area. More accurate than average end area method (which overestimates for tapering sections). Prismoidal correction is always negative (subtract from average end area result). Used in road/dam/canal earthwork estimates.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account