The area of oxidation ponds is determined on the basis of the following approximate rule:

Environmental EngineeringEnvironmental EngineeringMEDIUM

Choose the correct answer

A

500 persons to one acre of pond area

B

1000 persons to one acre of pond area

C

1500 persons to one acre of pond area

D

2000 persons to one acre of pond area

Correct Answer

B. 1000 persons to one acre of pond area

Why is this the answer?

Design thumb rules relate population served to pond area; official key B