Temperature correction in tape measurement is positive when field temperature is:

SurveyingSurveying and GeomaticsMEDIUM

Choose the correct answer

A

Higher than standard temperature

B

Lower than standard temperature

C

Equal to zero Celsius

D

Not recorded

Correct Answer

A. Higher than standard temperature

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Tape expands at higher temperature, so actual tape length increases and correction is positive.