In one cubic metre of 1:2:4 cement concrete mixed by volume, the number of cement bags required will be about
RCCRCCMEDIUM
Choose the correct answer
A
1
B
5
C
6
D
11
Correct Answer
C. 6
Why is this the answer?
1 m3 of 1:2:4 concrete needs about 6 cement bags.