Correction for pull is
SurveyingSurveyingMEDIUM
Choose the correct answer
A
(P-P₀)L/AE
B
(P-P₀)A/E
C
(P-P₀)EAL
D
(P-P₀)A×L/IE
Correct Answer
A. (P-P₀)L/AE
Why is this the answer?
Tape pull correction equals (P-P₀)L/(AE)
Related Surveying MCQs
More solved Surveying questions for AE/JE Civil Engineering exams.
- 'Contour interval' selection for a topographic survey depends on:
- A 'Digital Elevation Model' (DEM) is used in GIS for:
- The 'EDM' (Electronic Distance Measurement) instrument measures distances using:
- The 'photogrammetric control' (ground control points) in aerial survey are required for:
- The 'corrections' applied to measured chain/tape lengths include all EXCEPT:
- The 'photogrammetric stereomodel' from two overlapping aerial photos allows...
Practice more Civil Engineering questions
This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.