As per IS 456:2000, the creep coefficient (φ) for concrete at 28-day loading is approximately:

RCCCreep CoefficientMEDIUM

Choose the correct answer

A

0.5 to 1.0

B

1.6

C

2.2

D

3.0

Correct Answer

C. 2.2

Why is this the answer?

IS 456:2000 Table 9: Creep coefficient for loading at 28 days = 2.2; for loading at 7 days = 3.0; for loading at 1 year = 1.1. Creep coefficient depends significantly on age at loading.