Civil Engineering MCQJE Level Civil Engineering
Which of the following about probabilistic activity duration is correct?
Construction ManagementPERTMEDIUM
Choose the correct answer
A
PERT is a soil test
B
pessimistic time is ignored
C
PERT uses only one fixed duration
D
expected time is commonly based on optimistic, most likely and pessimistic estimates
Correct Answer
D. expected time is commonly based on optimistic, most likely and pessimistic estimates
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
PERT handles uncertainty in activity durations. Correct option: D.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.