Which of the following about probabilistic activity duration is correct?

Construction ManagementPERTMEDIUM

Choose the correct answer

A

PERT uses only one fixed duration

B

PERT is a soil test

C

expected time is commonly based on optimistic, most likely and pessimistic estimates

D

pessimistic time is ignored

Correct Answer

C. expected time is commonly based on optimistic, most likely and pessimistic estimates

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PERT handles uncertainty in activity durations. Correct option: C.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account