Which of the following about deterministic project scheduling is correct?
Construction ManagementCPMEASY
Choose the correct answer
A
critical path has zero total float in the basic network
B
float is measured only in rupees
C
critical path is always the shortest path
D
CPM ignores activity durations
Correct Answer
A. critical path has zero total float in the basic network
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
CPM identifies activities controlling project duration. Correct option: A.