Which of the following about delay without affecting successor early start is correct?
Construction ManagementFree FloatHARD
Choose the correct answer
A
free float is concrete slump
B
free float cannot exceed total float
C
free float ignores successors
D
free float is always larger than project duration
Correct Answer
B. free float cannot exceed total float
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Free float concerns immediate successor timing. Correct option: B.