Which of the following about cost and schedule performance is correct?
Construction ManagementEarned ValueMEDIUM
Choose the correct answer
A
actual cost is never recorded
B
earned value uses only rainfall
C
earned value compares planned value, earned value and actual cost
D
schedule variance is always zero
Correct Answer
C. earned value compares planned value, earned value and actual cost
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
EVM integrates scope, cost and schedule progress. Correct option: C.