Which of the following about cost and schedule performance is correct?

Construction ManagementEarned ValueMEDIUM

Choose the correct answer

A

actual cost is never recorded

B

earned value uses only rainfall

C

earned value compares planned value, earned value and actual cost

D

schedule variance is always zero

Correct Answer

C. earned value compares planned value, earned value and actual cost

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

EVM integrates scope, cost and schedule progress. Correct option: C.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account