Civil Engineering MCQJE Level Civil Engineering

Which of the following about allowable delay of an activity is correct?

Construction ManagementTotal FloatMEDIUM

Choose the correct answer

A

it is independent of network logic

B

it is the time an activity can be delayed without delaying project completion

C

it is always negative

D

it equals direct cost

Correct Answer

B. it is the time an activity can be delayed without delaying project completion

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Total float measures scheduling flexibility. Correct option: B.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account