Which of the following about adjusting schedule to smooth resource demand is correct?
Construction ManagementResource LevellingMEDIUM
Choose the correct answer
A
non-critical activities may be shifted within float
B
critical activities are always deleted
C
resource demand is ignored
D
levelling means changing concrete level only
Correct Answer
A. non-critical activities may be shifted within float
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Resource levelling balances resource usage against schedule. Correct option: A.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.