When crashing a project to reduce its duration, the correct strategy is to first crash:
Choose the correct answer
The activity with the longest duration
A critical activity with the lowest cost slope
Any non-critical activity to create float
The activity with the highest direct cost
Correct Answer
B. A critical activity with the lowest cost slope
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Only crashing critical activities reduces project duration. Among critical activities, the one with the lowest cost slope (cheapest to crash per unit time saved) is crashed first. Non-critical activities have float — crashing them wastes money. This iterative process continues until desired duration is achieved.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.