Total float of an activity is the amount by which it can be delayed without delaying:
Construction ManagementConstruction Materials, Practices, Planning and ManagementHARD
Choose the correct answer
A
the preceding activity
B
only its earliest start
C
project completion
D
only material delivery
Correct Answer
C. project completion
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Total float is the permissible delay in an activity without increasing the overall project duration.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap